A buyer in New York confirmed 600 pieces on 12 September for a 20 October launch and received them on 3 November. The mould was ready; the plating queue was not.
A production date is a sequence of queues rather than a single duration, and each queue has its own capacity limit.
[1]The five queues
Every order passes through CAD, mould or master, casting, finishing and plating. Each queue has a different lead time and a different way of absorbing delay.
| Stage | Typical lead time | Delay risk |
|---|---|---|
| CAD and approval | 3 to 7 days | Revisions |
| Master and mould | 5 to 10 days | Cutting queue |
| Casting | 3 to 5 days | Metal supply |
| Finishing | 5 to 8 days | Bench capacity |
| Plating | 2 to 5 days | Bath queue |
The table adds to 18 to 35 days for one order in isolation. Two orders in the same plating bath do not run in parallel, so the queue is where the calendar slips.

[2]Why the plating queue slips
A plating line runs batches, and a batch is set by the bath volume rather than by the order size. A 50 piece order and a 500 piece order may take the same bath, which means the small order waits for the large one to fill the line.
That is why a 50 piece order can take as long as a 300 piece order, and why the same 50 pieces can ship in 15 days when the line is empty and 25 days when it is not.
How to book capacity
Book the plating slot with the order rather than after the casting. A slot held in advance is the single most effective way to protect a launch date.
[3]Metal supply
Silver and gold are bought against the order, and a price move can delay a purchase decision. A buyer who fixes the metal price at order confirmation removes that delay from the schedule.
The alternative is a fluctuating quote, which is a schedule risk disguised as a price risk.
Stone availability
A lab grown parcel and a coloured stone parcel are both bought to the order. A colour match that takes two weeks is two weeks added to the schedule, and it happens before casting rather than after.
[4]The calendar windows
Chinese New Year closes factories for two to three weeks, and the week before the closure is the busiest of the year. An order placed in December for a February delivery is an order placed into the busiest queue.
National Day in early October closes for one week, and the same pattern applies at a smaller scale.
The buffer
A launch order should carry a 10 day buffer on the quoted date. A quoted date with no buffer is a date that assumes every queue performs at its best.
The buffer belongs after the plating stage rather than after the freight, because the two delays behave differently. A plating delay is recoverable by air freight; a freight delay is not recoverable at all.
[5]Capacity by quantity band
Capacity is not linear in quantity, because each stage has a setup cost that is paid once per run. A 50 piece run and a 500 piece run both pay for the mould, so the 50 piece run costs more per piece and takes the same calendar time as a 150 piece run.
That is why the price breaks sit at 200 and 500 pieces rather than at round numbers, and why a 120 piece order is usually quoted at the 200 piece rate.
What the band means for scheduling
Within one band the calendar is fixed by the queues rather than the quantity. Above 500 pieces the casting is split into multiple runs and the calendar extends.
[6]Order confirmation checklist
Five items should be confirmed in writing before production starts: the golden sample, the tolerance sheet, the stone record, the metal price and the plating slot.
Each of those is a queue that can stall, and each stall adds days to a date the buyer has already committed to someone else.
What goes wrong without it
The most common failure is a stone grade agreed verbally and a parcel bought to a different grade. It is discovered at inspection and the order is delayed by the time it takes to re-buy.
The second most common is a plating colour agreed from a photo, which is the one specification that cannot be transmitted by image. A physical standard or a Pantone reference is the only way to fix a white plate colour.
[7]Freight and customs time
A production date is not a delivery date. Sea freight adds 25 to 40 days to a US port, air adds 5 to 8 days, and customs adds 1 to 5 days depending on the entry.
Buyers who plan a launch from the production date alone are usually late by the freight time, which is the largest single block in the schedule.
The documentation that clears customs
An invoice, a packing list, a material declaration and a country of origin statement. A missing declaration holds a shipment for days, and it is the most common customs delay for jewellery.
The invoice value also has to match the declared value, because a mismatch triggers a hold that costs more than the duty saved. That is a paperwork discipline rather than a negotiation.
[8]Rush orders and what they cost
A rush order shortens a queue by displacing another order, which is a cost to the factory rather than a favour. That is why rush work carries a premium rather than a promise.
The realistic saving is 5 to 8 days on a 30 day schedule, and only if the plating slot is available. A rush that requires a new mould cannot save more than the casting time, because the mould queue is already the bottleneck.
Where a rush can actually help
Finishing and plating, because those are the queues with the most elasticity. Casting and mould work are limited by the number of benches and machines, which a rush cannot add.
[9]What a realistic date looks like
A 500 piece order confirmed on the first of the month ships at the end of the following month, which is 35 to 45 days plus freight. The number is not a delay; it is the length of the five queues in sequence.
A date quoted inside 20 days for a new design is a date that ignores the mould queue or the plating queue, and one of the two will appear at the end.
[10]What we quote
We quote the date by stage rather than as a single number, so the buyer can see which stage is at risk. Where a launch date is fixed, we book the plating slot at confirmation and state the date the order must be confirmed by.
Minimum order is 50 pieces per design and sizes can be mixed. Sample lead time is around 20 days from approved CAD, bulk 25 to 30 days, and stock designs ship in 15 to 20 days under 500 pieces. Payment is a 30 percent deposit with the balance before shipment, by T/T, PayPal or Western Union, with volume pricing at 200 and 500 pieces.
[11]The cost of a missed window
A missed launch window costs more than the freight difference between sea and air, because the season does not wait. A holiday order that arrives in January has lost its season rather than its date.
That is why the confirmation deadline matters more than the quoted date. A date can slip by a week without consequence in June and by a week with the whole season lost in November.
The buyer should state the season and the deadline at the quote stage, and the factory should quote backwards from it rather than forwards from the order.
[12]What the buyer controls in the schedule
Three things: the approval speed, the specification clarity and the confirmation date. Everything else is queue time the buyer cannot compress.
An approval that takes two weeks adds two weeks to the calendar, and it is the only stage where a buyer's own pace decides the date. A specification that changes after the master is cut resets the mould queue.
Buyers who complain about delivery dates are usually looking at the two stages they control and treating them as the factory's work.
[13]Frequently Asked Questions
Why does a 50 piece order take as long as 300 pieces?
Because plating runs in batches sized by the bath rather than the order. The small order waits for the bath to be scheduled.
How long before Chinese New Year should I order?
Six weeks. The two weeks before the closure are the busiest of the year and queues run at their worst.
Can the plating slot be booked in advance?
Yes, at order confirmation. Booking it at casting time is what causes most late launches.
Does fixing the metal price help the schedule?
Yes. It removes a purchase decision from the critical path, which is usually a two to five day delay.
[14]Next step
Send the launch date and the quantity, and we will quote the schedule by stage and the confirmation deadline. See OEM work in the archive, read the journal on sample approval, or open a brief on the contact page.