OEM Order Change Cutoff in Production
A brand in Manhattan changed a stone size on 200 rings two days before the ship date and received 200 pieces that could not be set, because the mountings were already cast.
An OEM order is changeable until a gate closes. The gates are set by the process rather than by goodwill, and a supplier that accepts a change after a gate is promising something the metal cannot deliver.
[1]The four gates
The gate list
CAD freeze, wax approval, casting and setting. Each gate closes a different category of change, and a change accepted after the gate becomes a remake rather than a revision.
A brand that knows the four dates can plan a launch around them. A brand that treats the schedule as elastic discovers the gates at the point of failure.
| Gate | Closes | Days before ship |
|---|---|---|
| CAD freeze | Shape, size, layout | 35 |
| Wax approval | Detail, crest, engraving | 28 |
| Casting | Metal, weight, size run | 20 |
| Setting | Stone, setting style | 12 |
The days are for a 50 to 200 piece run on a 25 to 30 day bulk schedule, and a smaller run has more room while a larger one has less.

[2]What a change after a gate costs
The cost of late
A size change after casting is a remake of the mounting, which is the metal plus the labour plus the lost casting. On a 200 piece run that is the batch rather than a piece, because the mould has already produced the waxes.
A stone change after setting is a reset, which is cheaper than a remake and still a bench hour per piece.
[3]The change that is free
A change before CAD freeze is free because nothing has been committed. That window is the one a brand should use, and it is usually three to five days rather than three weeks.
A brand that approves a CAD late has shortened its own window, which is the most common cause of a late change.
[4]How to write the schedule
The purchase order should carry the four dates rather than the ship date alone, and each date should name the change it closes. A schedule with one date gives a brand no way to know what is still possible.
A supplier who will not put the four dates in writing is a supplier who will accept a change and then miss the ship date, which is worse than a refusal.
[5]The change that should be refused
A change that would move the ship date should be refused or re-quoted, because a supplier that absorbs it moves every other order behind it. That is a scheduling decision rather than a service one.
A buyer should expect a re-quote rather than a yes, and a supplier that says yes to everything is a supplier whose dates are not real.
[6]What we do
We issue the four gate dates with every purchase order, accept changes before CAD freeze at no charge, and re-quote rather than absorb a change after casting. A change that moves the ship date is quoted with the new date.
Minimum order is 50 pieces per design and sizes can be mixed. Sample lead time is around 20 days from approved CAD, bulk 25 to 30 days, and stock designs ship in 15 to 20 days under 500 pieces. Payment is a 30 percent deposit with the balance before shipment, by T/T, PayPal or Western Union.
[7]The approval that starts the clock
The CAD freeze date is the moment the brand's approval is signed and not the moment the CAD is sent. A brand that reviews for a week has moved its own freeze date by a week.
A supplier should state the freeze date as the date the approval is received, and a brand should plan the review into the schedule rather than into the margin.
A late approval is the most common cause of a rushed run, and it is entirely within the brand's control.
[8]The wax that catches a detail
A wax approval catches a detail that a CAD cannot show, which is the depth of a crest and the sharpness of an edge. A brand that approves a CAD and skips the wax has approved a drawing rather than a piece.
The wax is cheap and it is the last point where a detail change is a change rather than a remake.
A brand that ships direct to retail should approve the wax on every new design and on every re-cut, because the re-cut is where a detail drifts.
[9]The metal that cannot be re-routed
A casting gate closes the metal as well as the shape, because the alloy and the size run are committed at the pour. A brand changing from 14K to 18K after the gate is changing the weight and the price.
The metal change is the one that a brand most often requests late, and it is the one that cannot be partly absorbed.
A supplier that accepts it has a scrap batch rather than a revised order.
[10]The stone that arrives late
A setting gate closes on the stones rather than on the mountings, and a brand that supplies its own stones late delays the setting rather than the casting.
That distinction matters because the brand controls the stone supply and often blames the factory for a delay it caused.
A purchase order should state who supplies the stones and when they arrive, because that date sets the setting gate.
[11]The schedule that has one date
A ship date alone tells a brand nothing about what can still change, which is why the four gates matter more than the delivery date on a first order.
A brand that plans a launch from a single date will discover the casting gate at the moment it needs a size change, and the discovery costs a batch.
[12]The change that is a new order
A change of metal, of size run and of stone type together is a new order rather than a revision, because all four gates reopen. A brand should expect a new sample and a new schedule rather than a resumed one.
That boundary is worth stating in the purchase order, because a brand and a supplier can disagree about whether three changes are one revision or three.
[13]The confirmation that is not an approval
A supplier's confirmation of receipt is not an approval, and a brand that reads a confirmation as an approval believes the freeze has passed when it has not. The freeze date starts on the signed approval rather than on the email.
A purchase order should name the approver, because an approval from an assistant who cannot commit the budget is not an approval.
[14]The gate that a brand can move
A brand can move its own CAD freeze date earlier by approving sooner, and it cannot move the casting date later without paying for a re-run. The two dates respond to different parties.
A launch that needs a late change should plan the run smaller and the re-order larger, because the first run carries the risk and the second one carries the volume.
A supplier who states both dates gives a brand the two levers it can actually pull.
[15]The re-quote that keeps the relationship
A re-quote on a late change is the answer that keeps a supplier's dates real and a brand's expectation honest. A supplier that re-quotes is not refusing, it is pricing.
A brand that hears a re-quote should compare it to the cost of a missed launch, which is usually higher.
[16]Frequently Asked Questions
When can an OEM order still be changed?
Freely before CAD freeze, at cost between freeze and casting, and not at all after casting without a remake.
How long before shipping is the last change date?
About 20 days on a 200 piece run, which is the casting gate. A stone change can go to 12 days.
What does a late change cost?
A remake of the mounting on every piece affected, which on a batch is the batch.
Why not accept a change and rush it?
Because it moves every order behind it. A re-quote with a new date is the honest answer.